TURNKEY TRAINING AND SAFETY FACILITY

This project was completed for a multinational corporate client heavily involved in the mining industry in the North West of Southern Africa.

Our client was initially intending to lease the property where the Training facility was to be situated and therefore required their entire facility to be Prefabricated AND Relocatable.

Timing for the project was also a major factor for our client therefore they opted for our Polycore Prefabricated Modular type building solution.

This choice of building format would allow them to occupy the facility and start training in a fraction of the time had they opted for the old school conventional brick and mortar type buildings.

The fully functional Turnkey Prefabricated Training facility comprised of 12 Prefabricated Buildings totalling 4012 square meters under roof.

The Prefabricated Buildings comprised of Offices, Lecture rooms, Board rooms, Conference facilities, Kitchen and Changeroom  facilities.

All aspects of the project were completed starting with the civil works preparation, concrete slabs, erection of the Prefabricated buildings and culminating in the sewer and electrical reticulation connections with all associated finishes.

The project was successfully completed within the projected time frame of 5.5 months.